Installation steps of industrial chillers

  Aug 12, 2020

  Leave a message

 

1. The place where the unit is installed must be the floor, installation mat or foundation, whose levelness is within 6.4mm, and can bear the operating weight of the unit.

2. The unit should be placed in a room with a room temperature of 4.4-43.3°C, and there should be enough space around and above the unit for daily maintenance.

3. At one end of the unit, there should be space for pipe extraction to clean the condenser tube bundle, and door openings or other suitable openings can also be used.

4. Choose the water pipe with proper pipe diameter, the cooling system and cold water system when the unit is running at maximum power, and connect them correctly.

5. For ordinary applications, the water flow speed through the evaporator and condenser is allowed to be between 1.0-3.6m/s.

6. Under any load conditions, the water flow should remain stable.

7. The design and installation of all chiller water and cooling water pipelines should be carried out according to conventional methods, and the chilled water pump should be located on the inlet pipe of the unit to ensure the positive pressure and flow in the unit. When piping, damping pipes should be installed to ensure proper flexibility, and to prevent water from the evaporator from being drained when the pump is stopped.

8. The pipeline should have a firm support independent of the chiller to avoid stress on the components of the chiller. The hanger should be set to facilitate pipe alignment.

9. In order to reduce noise and vibration, it is best to install vibration isolators on the pipeline.

10. In order to use industrial chillers economically and effectively, it is recommended to ask water treatment experts to analyze the water quality of the evaporator and condenser. Poor water quality will cause fouling and affect heat transfer, or produce corrosion deposits, breed organic matter, and affect the performance of the unit. , Increase operation and maintenance costs.

11. Generally speaking, proper water treatment and regular cleaning of the tube bundle can maintain its good performance. If the existing water quality conditions cannot be improved by appropriate methods, then it is necessary to consider allowing the tube bundle to have a larger fouling factor or specify Specialized structural materials.

12. Install a filter at the entrance of the water pipe and clean it regularly.

13. After the leak test is completed, all the nozzles must be treated with rust prevention.

14. In order to facilitate daily maintenance work, users can take the following measures:

a) Pressure gauges and stop valves with plugs can be installed on the inlet and outlet pipes of cooling water and chilled water, as close as possible to the chiller;

b) Hanging rails and beams can be erected above the equipment to facilitate maintenance.